where the responded has failed to provide a payment schedule
The adjudication application must be lodged with Adjudicate Today (or other Authorised Nominating Authority [ANA]) within 10 business days after the 5 business days from receipt of the s17.2 notice has expired. A contract provision which seeks to pre-select the ANA is void and has no effect.
An adjudication application must:
- Be in writing addressed to Adjudicate Today (or other ANA), requesting the nomination of an adjudicator;
- At the same time be served upon the respondent;

- Attach a copy of the payment claim;
- Contain and have attached to it all the information (including expert reports, photographs and arguments) which the claimant wants to put to the adjudicator in support of the claim; and
- Include a copy of the contract or all relevant contract terms and conditions.
An adjudication application should NOT speculate on possible reasons for non-payment of a claim if there is no payment schedule.
Download the Adjudication Application form
*Note: This form is interactive. This means it can be EITHER filled out on screen and printed OR downloaded and printed for manual completion.
The Act requires the payment of an ANA's prescribed application fee when the application is lodged. The prescribed application fee charged by Adjudicate Today is NIL ($0:00) dollars.
The claimant should attach to the application copies of:
-
The construction contract (which may be a formal contract document, an exchange of letters, a quotation and acceptance or a record of an oral agreement) under which the payment claim is made.
-
The payment claim.
-
Any supporting documents (eg certificates, test results, delivery dockets, invoices, photographs, statutory declarations, expert reports, written statements, etc).
-
A written submission evidencing that the claimed amount is due and unpaid and evidencing the value of the work, materials or services for which payment is claimed.
The submission should clearly state why the monies are owed and include supporting material as to why the claimant is entitled to the particular amount claimed.
In relation to preparing the adjudication application:![]()
-
Show that the work was in fact done and/or related goods and services were supplied as required by the provisions of the contract or agreement between the parties in accordance with the identified items and conditions of the contract (if possible, refer to the specific paragraph in contract).
-
Ensure a copy of the contract is attached. If the contract or agreement is wholly or partly oral, set out the precise terms of the oral agreement, when it was made and the named person who entered the contract on behalf of the respondent. Attach a copy of the written part of the contract or agreement.
-
If the contract is not a formal contract but the result of letters or other correspondence, attach copies of the relevant letters and/or correspondence which constitute the contract or agreement.
-
Show the nature and extent of the work done (including any rectification work of alleged defects) and/or related goods and services provided by the claimant under the contract and quantify their value.
-
Clearly set out calculations showing how the amount claimed is made up by items/value with a total, including GST.
-
If possible obtain witness statements or other technical report, test results, photos, invoices (from suppliers, quality assurance statements, statutory declarations of payment of workers subcontractor etc) or other documentation which supports the claim, attach these as numbered attachments. This is particularly important for larger claims. These attachments should show that the work was properly done and completed in line with the contract and/or that related goods and services were provided as per the progress claim.
-
Set out in separate numbered paragraphs the arguments with logical reasons as to why the claimant is entitled to receive the amount claimed as a progress claim. Refer back to any relevant material supporting each argument and quote the specific attachments (e.g. see Report dated… Attachment A etc).
-
Any legal advice and/or opinion which supports the claim may be attached as an annexure and should be referred to in the submission (a legal opinion is not necessary to make a claim).
-
Ensure that submissions do not contain emotional words or language derogatory or defamatory of the respondent.
The overall submission should be concise, clearly written and set out the claimant’s arguments and reasons. Remember the submission should always link back to any agreement/documentation, photos, technical/legal reports which support the claimant’s entitlement as set out in the payment claim.
A copy of the adjudication application and all attachments or other things accompanying it must be served on the respondent at the same time as it is served upon Adjudicate Today.
Please move to the next step on the "Payment Schedule NOT served flowchart" being "Claimant serves Adjudication Application on Adjudicate Today and Respondent".
or
