A reference date needs to be identified before a payment claim is made under the Act. This date is normally easy to identify but some contracts make the easy difficult!
A reference date is either the date for making progress claims as stated in the contract, or if the construction contract does not say, it is the last day of each named month.
A claimant can only give the respondent a progress claim on and after each reference date. Also the sum claimed for work performed can only be for work performed up to the reference date. Claiming for work performed after a reference date may render the whole payment claim invalid.
The reference date may be determined by a term in the construction contract or if there is no express term then the Act defines it as the last day of the month. So:
| If the construction contract DOES stipulate a time (e.g. the 10th day of the month) that a progress claim can be made | That date is the reference date |
| If the construction contract DOES NOT make any stipulation about when a progress claim can be made | Then the reference date is the last day of the month in which work was performed and the last day of each subsequent month. |
Sometimes a construction contract requires progress claims to be made at different stages of work. This sort of contractual provision is usually referred to as milestone payments. The claimant must check the construction contract to establish reference dates when ‘milestone payments’ are relevant.
Once the reference date has been identified, a progress claim can be prepared and served for work performed (or related goods and services provided) to that date.
Once the reference date has been identified, a payment claim can be prepared and served for work performed to that date.
A payment claim is a progress claim (invoice) which allows recovery of money owed using the Act.
It must:
A claimant is a person who has carried out construction work, or supplied related goods and services, and is or claims to be entitled to a payment claim under a construction contract. e.g. any sub-contractor who renders a progress claim for payment is a claimant.
Ensure the payment claim is addressed to the legal entity that the claimant contracted with (the respondent). It is no use seeking an adjudication determination against a respondent if the name and/or ACN/ABN is incorrect. Courts won't enforce determinations unless the name and ACN/ABN of the respondent match. Here are three examples (with names changed) of problems encountered.
Those who can make a payment claim under the Act include:
Construction work and services can be claimed under the Act even if the contract is not written and/or does not provide for progress payments. e.g. a single payment to be made when work is completed.
Unless the construction contract provides for a longer period, the claimant has 12 months to serve a payment claim on the respondent from the time construction work was last carried out or the related goods and services were last supplied.
Construction work and the supply of related goods and services includes:
A claimant can make a payment claim on the respondent for:
No. The Act does not apply to homeowners if the homeowner is party to the contract and resides or intends to reside in the building. These contracts are controlled by the Home Building Act 1989. Further information is available on the Fair Trading website (click here).
However:
An adjudicator can't determine an amount greater than claimed. If the claim is for $10,000 worth of work and all work performed is subject to GST, claim $11,000 inclusive of GST.
A payment claim should include all information necessary for a respondent to both identify the work and how the sum claimed is calculated. During adjudication, some respondents have successfully argued that they could not approve payment because the work claimed was so vague as to make it impossible to be confidently valued.
Where available, payment claims should include attachments such as:
Download template of a Payment Claim
Note: Our template retains the statement "This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 NSW". Including it does no harm while excluding it means that payment claims made, in relation to disputes over contracts made before 21 April 2014 or contracts which relate to a property where the owner resides or intends to reside and the owner did not contract directly with the claimant, are invalid.
Service should occur during normal business hours, at the respondent's ordinary place of business or as otherwise required by the contract. In the absence of a contrary contract provision, the safest way of ensuring service is to serve by courier with instruction to obtain a signed receipt. In our experience, below is the safest ranking to ensure service:
Tips:
Click here for a list of common reasons why adjudication applications by claimants fail.
A claimant is entitled to be paid a valid progress payment claim by the due date for payment.
The due date for payment is the date on which a payment claim becomes due and payable in accordance with the terms of the contract. However for most, but not all contracts, the Act sets a maximum time period for the due date of payment which overrides any contractual provision which is longer.
Unless the contract provides for a shorter period, a progress payment:
However if the contract was made before 21 April 2014 or applies to a residential property in which the owner resides, or intends to reside, and the contract was NOT made directly with the owner, a progress payment becomes due and payable an accordance with the terms of the contract (i.e. the 15/30 day maximum period does not apply) or, if the contract makes no provision, 10 business days after a payment claim has been made.
Calculating the due date for payment correctly is important because, if there is a payment dispute, certain rights and privileges are calculated from that date.
Click here for help in calculating the due date for payment.
The next step in our flowchart provides crucial information for both claimants and respondents. Depending on whether a respondent does or does not provide a payment schedule to the claimant within 10 business days' results in different time frames and procedures.
The respondent who fails to provide a payment schedule within 10 business days must be given a second opportunity to provide one. If it fails a second time, the Act effectively punishes the respondent by denying it the right to participate in the adjudication process.
Please move to the next step on the flowchart being "Respondent has 10 business days after receipt of the Payment Claim (or shorter period if provided by construction contract) to prepare and serve a Payment Schedule".
A claimant may take a lien or charge over unfixed plant or materials supplied by the claimant for or in connection with the carrying out of the construction work.
A lien is the right to seize and sell goods in order to obtain payment. If the goods are sold for more than the amount owed under the Act then the balance must be paid to the respondent. The lien granted by the Act does not give the claimant preference over a lien or charge existing before the date upon which the progress payment became due. It does not give the claimant any rights where a third party owns the items.
Before exercising a lien, legal advice should be obtained to ensure that there is no trespass upon the rights of others, which may cause the claimant to incur legal liability.
