A person who, under a construction contract, has undertaken to carry out construction work or to supply related goods and services is entitled to receive a progress payment for work performed.
The claimant (the person claiming a progress payment) may serve a payment claim on and from the last day of the named month in which the construction work was first carried out (or related goods and services were first supplied) under the contract and on and from the last day of each subsequent named month.
However, if the construction contract makes provision for an earlier date in a named month (e.g. 25th of the month), then that will be the applicable date rather than the last day of the month.
If a construction contract has been terminated, a payment claim can be served on and from the date of termination.
Unless the construction contract provides for a longer period, a progress claim must be made within 12 months after the construction work to which the claim relates was last carried out or the related goods and services to which the claim relates were last supplied. It is not uncommon for construction contracts to provide for longer periods. One example is a contract which provides for a 12 month defects liability period and that the final claim for payment should be made within 28 days after the end of the defects liability period. In this example, the contract has extended the period for the making of the final payment claim from 12 months to 12 months plus 28 days. A contract can't reduce the 12 month period allowed by the Act.
A claimant must not give more than one payment claim for each calendar month, unless the construction contract provides for more than one payment claim to be given in a calendar month. However, this does not prevent the claimant from:
A payment claim is a progress claim (invoice) which allows recovery of money owed using the Act.
It must:
A claimant is a person who has carried out construction work, or supplied related goods and services, and is or claims to be entitled to a payment claim under a construction contract. e.g. any subcontractor who renders a progress claim for payment is a claimant.
Ensure the payment claim is addressed to the legal entity that the claimant contracted with (the respondent). It is no use seeking an adjudication decision against a respondent if the name and/or ACN/ABN is incorrect. Courts won't enforce decisions unless the name and ACN/ABN of the respondent match. Here are three examples (with names changed) of problems encountered.
Those who can make a payment claim under the Act include:
Construction work and services can be claimed under the Act even if the contract is not written and/or does not provide for progress payments. e.g. a single payment to be made when work is completed.
Construction work and the supply of related goods and services includes:
A claimant can make a payment claim on the respondent for:
No. The Act does not apply to homeowners if the homeowner is party to the contract and resides or intends to reside in the building.
However:
Important qualification: The definition of resident-owner under section 9(7) of the Act does not include a person who is or should be licenced as an owner-builder under the Construction Occupations (Licensing) Act 2004. Therefore an owner-builder qualifies as a respondent and may be served with a payment claim.
For further information on Owner-Builders
An adjudicator can't decide an amount greater than claimed. If the claim is for $10,000 worth of work and all work performed is subject to GST, claim $11,000 inclusive of GST.
A payment claim should include all information necessary for a respondent to both identify the work and how the sum claimed is calculated. During adjudication, some respondents have successfully argued that they could not approve payment because the work claimed was so vague as to make it impossible to be confidently valued.
Where available, payment claims should include attachments such as:
Download template of a Payment Claim
Service should occur during normal business hours, at the respondent's ordinary place of business or as otherwise required by the contract. In the absence of a contrary contract provision, the safest way of ensuring service is to serve by courier with instruction to obtain a signed receipt. In our experience, below is the safest ranking to ensure service:
Click here for a list of common reasons why adjudication applications by claimants fail.
A claimant is entitled to be paid a valid progress payment claim by the due date for payment.
The due date for payment under the Act is the earlier of 15 business days** after a payment claim is given, or the day when the payment becomes payable under the contract. If the contract provides that payment is due 10 days after invoice then, upon service of the payment claim, the due date for payment under the Act is 10 days later. Any term of a contract that provides for a due date for payment later than 15 business days will have no effect for the purposes of the Act. Proper calculation of this date is imperative as a number of milestones under the Act are calculated from this date.
Endorsing all invoices as a payment claim ensures that claimants don't need to wait for additional, often lengthy, periods before seeking recovery of debts under the Act. The due date of payment under the Act (regardless of any contract provision) can't occur prior to service of the payment claim. If the claimant is not paid by the due date, they have a right to interest at the greater of the rate, if any, in the contract or the rate on Supreme Court judgments. The Supreme Court rate changes from time to time but is usually around 10% per annum.
The next step of our flowchart provides crucial information for both claimants and respondents. Up until this time the Act's time frames and procedures were the same. However they now diverge based on whether the respondent does or does not provide a valid payment schedule to the claimant.
The respondent who fails to provide a payment schedule must be given a second opportunity to provide one. If they fail a second time, the Act effectively punishes the respondent by denying them the right to participate in the adjudication process. This results in the two different procedures which affect the interests and actions of both claimants and respondents. These procedures are fully described in the next step on the flowchart.
Please move to the next step on the flowchart being "Respondent has 10 business days after receipt of the Payment Claim (or shorter period if provided by construction contract) to prepare & serve a Payment Schedule".
The Act also provides that a claimant may take a lien or charge over unfixed plant or materials supplied by the claimant to the respondent for or in connection with the carrying out of the construction work.
A lien is the right to seize and sell goods in order to obtain payment. If the goods are sold for more than the amount owed under the Act then the balance must be paid to the respondent. The lien granted by the Act does not give the claimant preference over a lien or charge existing before the date upon which the progress payment became due. It does not give the claimant any rights where a third party owns the items. Generally speaking, when a principal pays a contractor for items, they become the property of the principal.
Before exercising a lien, legal advice should be obtained to ensure that there is no trespass upon the rights of others and thereby incur a liability to a third party.
Unless the construction contract provides for a longer period, a payment claim under the Act must be made within 12 months after the construction work to which the claim relates was last carried out or the related goods and services were last supplied.
**We note that the ACT Government has advised that the βthe changes to the Building and Construction Industry (Security of Payment) Act 2009, which commenced on 11 March 2024 (and relevantly change the timeframe from 10 business days to 15 business days), apply to any progress claim made under the Act from 11 March 2024, regardless [of] when the contract was signed.β This issue will remain unsettled until it is considered by the Courts.