A payment response (the Act calls this a notice of dispute) need only be prepared if the respondent does not propose to pay the full amount claimed by the due date for payment.
A notice of dispute is the notice in writing which should be served on the applicant by the respondent if the respondent does not intend to pay the full or part of a claimed amount by the due date for payment. This applies even if the respondent believes the applicant is not entitled to make the claim or if the respondent denies being party to the contract.
The due date for payment is usually set out in the contract. It can be any period up to 42 days after receipt of the payment claim. In the absence of an explicit contractual provision, the Act implies the due date for payment is 14 days after receipt of the payment claim.
A notice of dispute must:
In the event that no notice of rejection or dispute is given, the payment claim must, subject to contract or if there is no written contract, be paid within 28 days of it being received.
A notice of dispute (the contract may give it another name) is not served until it is received by the applicant or lodged during normal business hours at the applicant's ordinary place of business, so that it reaches the applicant no later than the due date for payment being 14 days after receipt of the payment claim.
The contract may amend the 28 days for payment of a payment claim from when it is received and the 14 day period for serving a notice of dispute, provided that the total of both periods does not exceed 42 days.
We recommend that a record of the time, date and manner of service on the applicant be kept. An applicant may deny receipt of the notice of dispute or claim receipt after the expiry of due date for payment. In this case, the respondent must be able to evidence the date of service.
With retention moneys and security, if there is nothing agreed to in the contract, then under the implied provisions of the CCA a contractor may claim for payment of retention moneys or the return of security if they have not occurred by the due date under the contract.
The applicant has a number of alternatives. Click here to go to 'Full or any part of claimed amount NOT paid by Due Date for Payment'.