An applicant can't make a valid adjudication application unless the payment process set out in contract has been followed. In many areas, but not all, the contract may substitute for information contained in this page. Therefore it is imperative to check the contract before relying on this information.
Where the contract is oral (not written) or does not contain provisions covering particular matters, the Act implies (bring in) terms into the contract.
Generally, a construction contract will contain express terms about the rights and obligations of the parties including:
Regardless of what is in contract, the Act specifically prohibits:
Where a construction contract is oral or does not have a explicit provision relating to any of the following than the Act implies (brings in) the applicable provision:
A payment claim is a claim for a progress payment under a construction contract or a claim for payment by the principal in relation to to the performance or non-performance by the contractor of its obligations under the contract. It must identify the construction work or related goods and services and the amount that the applicant claims to be payable. It may include matters covered by a previous payment claim but not identical claims previously valued by an adjudicator.
Self evidently, a payment claim is not an estimate of costs nor is giving notice of a payment claim, a payment claim.
The Act implies the following terms into the contract with regard to how a payment claim should be made:
Regardless of any other specific requirements in the contract, it is wise to also include all the above information and information about the respondent (next heading below).
Ensure the payment claim is addressed to the legal entity that the applicant contracted with (the respondent). If there is an address or email etc. in contract for service, it is that address or email etc. If there is no address in contract, send the payment claim to the registered office of the respondent or an email which the parties have agreed should be used for all correspondence. Also, it is no use seeking an adjudication determination against a respondent if the name and/or ACN/ABN is incorrect. Courts won't enforce determinations unless the name and ACN/ABN of the respondent match. Here are three examples (with names changed) of problems encountered.
Those who can make a payment claim under the Act include:
Work performed on a site in WA, notwithstanding the contract containing any provision that the contract is governed by law of a place other than WA.
The detailed scope of construction work is found in section 4 of the Act. Generally, construction work and the supply of related goods and services includes:
An applicant can make a payment claim on the respondent for:
Yes. an applicant can make a payment claim on a homeowner.
An adjudicator can't determine an amount greater than claimed. If the claim is for $10,000 worth of work and all work performed is subject to GST, claim $11,000 inclusive of GST.
A payment claim should include all information necessary for a respondent to both identify the work and how the sum claimed is calculated. During adjudication, some respondents have successfully argued that they could not approve payment because the work claimed was so vague as to make it impossible to be confidently valued.
Where available, payment claims should include attachments such as:
Service should occur during normal business hours, at the respondent's head office or as otherwise required by the contract. In the absence of a contrary contract provision, the safest way of ensuring service is to serve by courier with instruction to obtain a signed receipt. In our experience, below is the safest ranking to ensure service:
Tips:
Please move to the next step on the flowchart being "Party receiving Payment Claim (the Respondent) has 14 days (OR OTHERWISE AS PROVIDED BY CONTRACT) from claim receipt to give the applicant Notice of a Dispute".
