Unless the contract otherwise provides, the Act implies that where a party receiving a payment claim (the respondent) believes the claim has not been made in accordance with the contract or disputes the whole or a part of the claim, a payment response (the Act calls this a notice of dispute) should be prepared by the respondent.
The default provision under the Act is that the notice of dispute must be provided within 14 days of receiving the payment claim but the contract may provide for any period up to 42 days. (Note the Act says 'days' not 'business days'; therefore counting of days continues on weekends, public holidays and over the Christmas shut down period).
A notice of dispute is the notice in writing which should be served on the applicant by the respondent if the respondent does not intend to pay the full or part of a claimed amount by the due date for payment. This applies even if the respondent believes the applicant is not entitled to make the claim or if the respondent denies being party to the contract.
The due date for payment is usually set out in the contract. It can be any period up to 42 days after receipt of the payment claim. In the absence of an explicit contractual provision, the Act implies the due date for payment is 28 days after receipt of the payment claim.
A notice of dispute must:
In the event that no notice of dispute is served, and in the absence of a specific contractual provision, the payment claim must be paid within 28 days of it being received, however the contract may extend this period up to 42 days (the due date for payment). A contractor may also claim for payment of retention moneys or the return of security, if they have not been paid once the due date for payment has passed.
Tips:
A common reason for respondents not agreeing to a payment claim is that they have not been paid by the principal. Effectively the respondent is imposing on the applicant an extension of payment terms. This defence of "pay when paid" or "pay if paid" is expressly barred by the Act, even if such right is included in the contract. The policy behind the Act is that a respondent should not cause an applicant financial detriment because of their problems. In any case, respondents can seek a remedy under the Act by serving a payment claim on the principal and, if not paid by the due date for payment, applying for adjudication.
Click here to go to "Respondent serves a Notice of Dispute within time". The blue shaded background of the flowchart describes how to proceed in these circumstances.
Click here to go to "Respondent FAILS to serve a Notice of Dispute within time". The pink shaded background of the flowchart describes how to proceed in these circumstances.
