Vic: Claimant Prepares Adjudication Application (Disputes Payment Schedule)

Schedule Served

This section provides guidance for the claimant in completing an adjudication application where the claimant has received a payment schedule which is for an amount less than that claimed.

What can't be adjudicated under the Act?

  • A construction contract that deals with construction work carried on outside Victoria or related goods and services supplied for construction work carried on outside Victoria. In this situation, an adjudication application should be made under the Security of Payment Act relevant to the State in which the work was performed.
  • A claim against a homeowner if the homeowner is party to the contract and resides or intends to reside in the building.
    However:
    • If a contract includes work other than on the respondent's immediate residence, then that work is subject to the Act. e.g. work involving a residential investment property;
    • If the owner did not contract directly with the claimant, then that work is subject to the Act. Examples include contracts with landlords, strata title bodies corporate, developers, builders, contractors, sub-contractors, consultants and suppliers.
  • A claim for damages for breach of contract. Also if the contract price exceeds $150,000 and the contract includes a dispute resolution clause there are restrictions on the amount claimable for disputed variations. These important and complex exclusions are fully detailed under the heading Excluded Amounts and Variation Claims.
  • A construction contract between parties to the extent that it forms part of a loan agreement, a contract of guarantee or a contract of insurance under which a recognised financial institution undertakes to lend or repay an amount lent; guarantee payment of an amount owing or repayment of an amount lent; or provide an indemnity relating to construction work carried out or related goods and services supplied.
  • Contracts in which the consideration payable for construction work carried out or related goods and services supplied under the contract, is calculated other than by reference to the value of the work or goods and services supplied.

An adjudication application must:

  • Be in writing addressed to Adjudicate Today, requesting the nomination of an adjudicator;

  • Be lodged with Adjudicate Today within 10 business days from the date of receipt of the payment schedule. However there is a trap! If the claimant served an adjudication notice, also called a second opportunity or section18(2) notice (only necessary if the respondent failed to serve the payment schedule within 10 business days of the payment claim), the adjudication application must be prepared and served by the claimant within 10 business days of the expiry of the section 18(2) notice. Service of an adjudication application on Adjudicate Today before the 2 business days after the respondent's receipt of the section18(2) notice has elapsed will render the application invalid.

  • Attach a copy of the payment claim;

  • If a section 18(2)] notice was served, attach a copy of that notice;

  • Attach a copy of the payment schedule;

  • Contain a written submission demonstrating that the claimed amount is due and unpaid and the value of the work, materials or services for which payment is claimed. The submission must also respond to the reasons, if any, given by the respondent for non-payment and must provide evidence or arguments to refute the respondent's grounds for withholding payment.

  • Have attached to the written submission all the information (including certificates, test results, delivery dockets, invoices, photographs, statutory declarations, expert reports, written statements and arguments) which the claimant wants to put to the adjudicator in support of the written submission and refuting any reasons, given by the respondent in the payment schedule, for withholding payment; and

  • Include a copy of the contract or all relevant contract terms and conditions. This may be a formal contract document, an exchange of letters, a quotation, an acceptance or a record of an oral agreement under which the payment claim is made.

  • The entire application must be served on the respondent. The copy must be identical to that provided to Adjudicate Today. Any delay in serving the respondent delays adjudication.

The Act requires the payment of an ANA's prescribed application fee when the application is lodged. The prescribed application fee charged by Adjudicate Today is NIL ($0:00) dollars.

When making your adjudication application you have 2 alternatives:

  1. Use our interactive lockbox which provides assistance for each necessary step, or;
  2. Complete the application manually using our adjudication application form (this can also be completed on your computer).

An adjudication application should not speculate on possible reasons for non-payment of a claim if they are not included, or alluded to, in the payment schedule.

It is usually not sufficient for the claimant to merely refer to the payment claim and the respondent's payment schedule and state that he/she is entitled to payment. The submission should:

  1. State that the work was in fact done and/or related goods and services were supplied as required by the provisions of the contract or agreement between the parties in accordance with the identified items and conditions of the contract (if possible, refer to the specific paragraph in contract).

  2. Attach a copy of the contract. If the contract or agreement is wholly or partly oral, set out the precise terms of the oral agreement, when it was made and the named person who entered the contract on behalf of the respondent. Attach a copy of any emails, correspondence or paid invoices supporting the oral agreement.

  3. If the contract is not a formal contract but the result of letters or other correspondence, attach copies of the relevant letters and/or correspondence which constitute the contract or agreement.

  4. Show the nature and extent of the work done (including any rectification work of alleged defects) and/or related goods and services provided by the claimant under the contract and quantify their value.

  5. Clearly set out calculations showing how the amount claimed is made up by items/value with a total, including GST.

  6. If possible obtain witness statements or other technical reports, test results, photos, invoices (from suppliers, quality assurance statements, statutory declarations of payment of workers subcontractor etc.) or other documentation which supports the claim, attach these as numbered attachments. This is particularly important for larger claims. These attachments should show that the work was properly done and completed in line with the contract and/or that related goods and services were provided as per the progress claim. Statutory declarations are not necessary. Because an adjudicator cannot test the contents of a statutory declaration, they are given no greater weight than unsworn witness statements.

  7. Set out in separate numbered paragraphs the arguments with logical reasons as to why the claimant is entitled to receive the amount claimed as a progress claim. Refer back to any relevant material supporting each argument and quote the specific attachments (e.g. see Report dated... Attachment A etc.).

  8. Any legal advice and/or opinion which supports the claim may be attached as an annexure and should be referred to in the submission (a legal opinion is not necessary to make a claim).

  9. Ensure that submissions do not contain emotional words or language derogatory or defamatory of the respondent.

The overall submission should be concise, clearly written and set out the claimant's arguments and reasons. Remember the submission should always link back to any agreement/documentation, photos, technical/legal reports which support the claimant's entitlement as set out in the payment claim.

How is an adjudication application served on Adjudicate Today?

Both Adjudicate Today and the respondent should be served with identical adjudication applications on the same day.

Service on Adjudicate Today can be made by any of the following methods:

  1. Electronic File Delivery via Lockbox. You can send very large electronic files directly to Adjudicate Today. All files are encrypted and sent over a secure connection. They are held in your personal 'Lockbox'. Only you and Adjudicate Today authorised staff can access your Lockbox. We strongly recommend it over email as email may not be received. All uploaded files are acknowledged by an automated email within a couple of minutes. If the date and time stamped email is not received, there has been a problem uploading. Please email our office: vic@adjudicate.com.au or phone 1300 760 297.

    Click here for details on establishing a free Lockbox account

  2. Electronic File Delivery via Email. vic@adjudicate.com.au.

  3. Electronic File Delivery via Fax: 1300 760 220. Adjudicate Today permits service of adjudication applications, notices and other documents by fax. Adjudicate Today permits service of adjudication applications, notices and other documents by fax.

    Following any form of electronic file delivery (Lockbox, email or fax), the claimant may be requested to provide Adjudicate Today with one (1) hard copy of any electronic files. Please read our disclaimer for details on rights and obligations for the delivery of electronic files.

  4. Physical Delivery. We accept delivery in any of our Australian offices (normal business hours). Our Vic address is Level 27, 101 Collins Street, Melbourne Vic 3000. A map to the Vic office and addresses of other State offices are found on our Contact Us page.

How is an adjudication application served on the respondent?

Service should occur during normal business hours and at the respondent's ordinary place of business or as otherwise required by the contract. In the absence of a contrary contract provision, the safest way of ensuring service is to serve by courier with instruction to obtain a signed receipt. In our experience, below is the safest ranking to ensure service:

  1. Courier - signature required;
  2. Mail - Express Post: keep express post tracking number for delivery verification;
  3. Platinum Post - Signature required;
  4. Ordinary Post - Make a statement verifying the address, date of postage and other relevant details;
  5. Email (only to an email address which is specified by the person for the services of notices of that kind - generally the claimant). In email options, we advise tick both "request a delivery receipt" and "request a read receipt";
  6. In person - Ensure a receipt is obtained; or
  7. A different method only where such method is provided under the relevant construction contract. Please note that service by fax is only valid if provided by the contract. If service by fax is permitted, print and keep full page fax journal report as evidence of transmittal.

Tips:

  • Claimants are strongly advised to keep a record of the time, date and manner of service on the respondent. The time for the respondent to provide the payment schedule (response) runs from the date of receipt of the payment claim. A respondent may deny receipt of the payment claim in which case the claimant must be able to evidence the date of service.
  • When items are sent by ordinary post, allow sufficient time for them to be received. Generally, items sent by ordinary post are deemed to be received on the fourth working day after posting. We recommend against post as respondents have denied receipt.
  • Should fax be permitted by contract as a form of service, ensure you retain the full page fax receipt and refrain from sending colour photographs, and plans as they are generally rendered unreadable. Lengthy faxes have been known to lose pages in transmission.

It is most important that the claimant keeps a record of the time, date and manner of service on the respondent as time runs from the date of service.

Upon receipt of the application, Adjudicate Today nominates an appropriate adjudicator from our panel of registered adjudicators to determine the matter. Adjudicators cannot be pre-appointed under a construction contract and parties must not seek to influence an ANA in appointing any particular adjudicator. The Supreme Court may invalidate any adjudication determination where a party has influenced an adjudicator appointment. However if parties agree to the appointment of a particular adjudicator after the adjudication application is filed, Adjudicate Today will seek to accommodate the agreement.

Within 4 business days of receipt of an application, Adjudicate Today will provide a formal Notification of Acceptance of the adjudication application on behalf of the appointed adjudicator. If this does not occur, the claimant can withdraw the application and has a further 5 business days to lodge another application.

Please move to the next step on the Victoria flowchart which is "Respondent has 5 business days to prepare & serve Adjudication Response on Adjudicate Today & Claimant from receipt of Application from Claimant or 2 business days after receiving notice of Adjudicator's acceptance of the Application, whichever is the later". Ensure you remain in the area of the flowchart with blue background.

print this page