Unless the construction contract provides for a longer period, a payment claim under the Act must be made within 3 months after the construction work to which the claim relates was last carried out or the related goods and services were last supplied.
Also, a reference date needs to be identified before a valid payment claim can be made under the Act. This date is normally easy to identify but some contracts make the easy difficult!
A reference date is either the date for making progress claims as stated in the contract, or if the construction contract does not say, it is 20 business days after the last reference date.
A claimant can only give the respondent a progress claim on and after each reference date. Also the sum claimed for work performed can only be for work performed up to the reference date.
Claiming for work performed after a reference date may render the whole payment claim invalid.
The reference date may be determined by a term in the construction contract or, if there is no express term, by the 20 business day default required by the Act.
| If the construction contract DOES stipulate a time (e.g. the 10th day of the month) that a progress claim can be made | That date is the reference date. |
| If the construction contract DOES NOT stipulate a time when a progress claim can be made | The reference date is 20 business days after construction work was first carried out or goods and services provided and, for subsequent reference dates, 20 business days after the previous reference date. |
Sometimes a construction contract requires progress claims to be made at different stages of work. This sort of contractual provision is usually referred to as milestone payments. The claimant must check the construction contract to establish reference dates when ‘milestone payments’ are relevant.
Once the reference date has been identified, a progress claim can be prepared and served for work performed (or related goods and services provided) to that date.
Once the reference date has been identified, a payment claim can be prepared and served for work performed to that date.
A payment claim is a progress claim (invoice) which allows recovery of money owed using the Act.
It must:
A claimant is a person who has carried out construction work, or supplied related goods and services, and is or claims to be entitled to a payment claim under a construction contract. e.g. any sub-contractor who renders a progress claim for payment is a claimant.
Ensure the payment claim is addressed to the legal entity that the claimant contracted with (the respondent). It is no use seeking an adjudication determination against a respondent if the name and/or ACN/ABN is incorrect. Courts won't enforce determinations unless the name and ACN/ABN of the respondent match. Here are three examples (with names changed) of problems encountered.
Those who can make a payment claim under the Act include:
Construction work and services can be claimed under the Act even if the contract is not written and/or does not provide for progress payments. e.g. a single payment to be made when work is completed.
Construction work and the supply of related goods and services includes:
A claimant can make a payment claim on the respondent for:
No. The Act does not apply to homeowners if the homeowner is party to the contract and resides or intends to reside in the building.
However:
An adjudicator can't determine an amount greater than claimed. If the claim is for $10,000 worth of work and all work performed is subject to GST, claim $11,000 inclusive of GST.
A payment claim should include all information necessary for a respondent to both identify the work and how the sum claimed is calculated. During adjudication, some respondents have successfully argued that they could not approve payment because the work claimed was so vague as to make it impossible to be confidently valued.
Where available, payment claims should include attachments such as:
Download template of a Payment Claim
Service should occur during normal business hours, at the respondent's ordinary place of business or as otherwise required by the contract. In the absence of a contrary contract provision, the safest way of ensuring service is to serve by courier with instruction to obtain a signed receipt. In our experience, below is the safest ranking to ensure service:
Click here for a list of common reasons why adjudication applications by claimants fail.
A claimant is entitled to be paid a valid progress payment claim by the due date for payment.
The due date for payment under the Act is the date on which a payment claim becomes due and payable either in accordance with the terms of the contract or, if there is no such valid provision, 10 business days after the payment claim is made. If the contract provides that payment is due 28 days after invoice then, upon service of the payment claim, the due date for payment under the Act is 28 days later. Proper calculation of this date is imperative as a number of milestones under the Act are calculated from this date.
Endorsing all invoices as a payment claim ensures that claimants don't need to wait for additional, often lengthy, periods before seeking recovery of debts under the Act. The due date of payment under the Act (regardless of any contract provision) can't occur prior to service of the payment claim. If the claimant is not paid by the due date, they have a right to interest at the greater of the rate, if any, in the contract or the rate on Supreme Court judgments. The Supreme Court rate changes from time to time but is usually around 10% per annum.
The next step of our flowchart provides crucial information for both claimants and respondents. Up until this time the Act's time frames and procedures were the same. However they now diverge based on whether the respondent does or does not provide a valid payment schedule to the claimant.
The respondent who fails to provide a payment schedule must be given a second opportunity to provide one. If they fail a second time, the Act effectively punishes the respondent by denying them the right to participate in the adjudication process. This results in the two different procedures which affect the interests and actions of both claimants and respondents. These procedures are fully described in the next step on the flowchart.
Please move to the next step on the flowchart being "Respondent has 10 business days after receipt of the Payment Claim to serve a Payment Schedule (or such shorter period if provided by construction contract) to prepare and serve a Payment Schedule".
The Act also provides that a claimant may take a lien or charge over unfixed plant or materials supplied by the claimant to the respondent for or in connection with the carrying out of the construction work.
A lien is the right to seize and sell goods in order to obtain payment. If the goods are sold for more than the amount owed under the Act then the balance must be paid to the respondent. The lien granted by the Act does not give the claimant preference over a lien or charge existing before the date upon which the progress payment became due. It does not give the claimant any rights where a third party owns the items. Generally speaking, when a principal pays a contractor for items, they become the property of the principal.
Before exercising a lien, legal advice should be obtained to ensure that there is no trespass upon the rights of others and thereby incur a liability to a third party.
