The Victorian Act has unique differences to similar Acts operating in all other States and Territories. The Act prohibits an adjudicator to determine many payment disputes which similar legislation allows in the rest of Australia.
Unless the construction contract provides for a longer period, a payment claim must be made within 3 months after the construction work to which the claim relates was last carried out or the related goods and services were last supplied. This contrasts to 6 months in SA and 12 months under other similar Acts.
In Victoria, a variation claim must fit within one of two classes of variation. The wording of the Act is complex* albeit summarised below:
If the contract does not provide a method of resolving disputes, the above applies without further complexity. However, where a contract contains a method of resolving disputes and either of the following two points are applicable, the dispute can't be adjudicated:
* The Victorian Supreme Court is not impressed with these provisions '...takes several readings to digest the steps required to apply the provision, and several more steps, combined with a respectable prowess in the science of numbers, to apply it to the case at hand. Although the confounding formula described in s 10A on a close reading is tolerably precise, it fails in the critical task of communicating the legislative stipulations in a ‘user friendly’ and readily comprehensible fashion to its intended audience...' Branlin Pty Ltd v Tony Totaro and others [2014] VSC 492.
Therefore a voluntary mediation process would not qualify as a dispute resolution clause under the Act.
Notwithstanding any of the above an adjudicator, in determining a payment claim, must not take into account:
Parties drafting a contract with a contract price exceeding $150,000 should give consideration to whether they wish to have variation disputes or some of them decided in arbitration or by expert determination instead of adjudication. What is better will depend upon the circumstances of the particular contract. Having some variation claims decided in adjudication and some by arbitration or expert determination may have peculiar consequences.
Adjudicate Today has available adjudicators to conduct an expert determination. However we call expert determination a 'private adjudication' It is not an adjudication under the Act and the Act has no application. It is a private arrangement between the parties and the adjudicator. If requested, Adjudicate Today can nominate an adjudicator for a private adjudication. The private adjudication could be under an expert determination clause in the contract or pursuant to an ad hoc agreement.
Further information on Private Adjudication.
